某金属矿区桥梁桩基础施工技术研究
DOI:
CSTR:
作者:
作者单位:

河北建设勘察研究院有限公司, 河北 石家庄 050030

作者简介:

刘双辰(1980-),男,汉,河北保定人,本科学历,高级工程师,从事岩土工程方面研究。

通讯作者:

中图分类号:

U445

基金项目:


A case study of the construction process of pile foundations for a bridge in a metallic mine area
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    某金属矿区施工的桥梁基础受到采空区、溶洞叠加影响,导致桩基础施工困难且成桩质量差。为了确保桩基础施工质量,提出采用压注混凝土方式对采空区、溶洞等进行预处理;在桩基础孔施工中采用钢护筒跟进方式确保桩基础钻孔施工质量。现场应用后,在矿区施工的桩基础后期检测质量结果均为Ⅰ类桩,取得显著应用成果。研究成果为其他类似情况下的桩基础施工提供了经验借鉴。

    Abstract:

    The mined-out areas of a metallic mine, complemented by karst caves, made the construction of the pile foundations of a bridge above very difficult and resulted in poor piles. To ensure file construction quality, it was proposed to inject concrete into the mined-out areas and the karst caves in question, and to use steel sleeve pipes to ensure the quality of foundation bore holes. After these measures were taken, foundation quality tests showed that all the piles were of Class I, hence very successful. This attempt thus brings useful experience to operations under similar circumstance.

    参考文献
    相似文献
    引证文献
引用本文

刘双辰.某金属矿区桥梁桩基础施工技术研究[J].中国矿山工程,2021,50(4):77-79.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2025-12-24
  • 出版日期:
文章二维码