利用矿山已有工程及设备情况下竖井提升系统方案研究
CSTR:
作者:
作者单位:

1.中冶国际工程集团有限公司, 北京 100028 ; 2.鞍钢集团矿业弓长岭有限公司井采分公司, 辽宁 辽宁 111000 ;3.中国恩菲工程技术有限公司, 北京 100038

作者简介:

杨国强(1984—),男,北京市人,工程师,主要从事工程项目管理和企业管理相关工作。

通讯作者:

中图分类号:

TD53

基金项目:


Research on comparison of vertical shaft lifting system scheme using existing engineering and equipment in mines
Author:
Affiliation:

1.MCC International Incorporation Ltd., Beijing 100028 , China ; 2.Ansteel Group Mining Gongchangling Jingxiakuang, Liaoning 111000 , China ;3.China ENFI Engineering Corporation, Beijing 100038 , China

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    本文针对某矿山在其资源量减少、竖井井筒已施工及部分设备已订货的背景下,对如何优配竖井提升系统方案展开研究,以减少投资。通过对比分析原方案(2套独立提升系统+井塔布置)与3种拟选方案(单套提升系统+井塔式布置、单套提升系统+井架式布置、利用已订货设备单套提升系统+塔式布置)的技术参数、投资成本及优缺点,结果发现:原方案虽投资最高,但设备已就位、改造量小,提升能力充足,可稳定完成任务,风险最低;单套系统方案(方案一、二)虽降低投资,但需设备退订(违约金风险)、井筒改造,工期紧张且施工风险高;方案三虽投资最低,但提升能力不足,无法满足需求。综上,最终方案的选定需视各项目的具体情况而定,依可靠性、生产稳定性与长期成本,本项目仍优选原方案。

    Abstract:

    The study focuses on selecting the shaft hoisting system for a mining operation facing reduced resource reserves, with the shaft already constructed and partial equipment ordered, aiming to minimize investment. By comparing the original design (two independent hoisting systems with tower arrangement) against three optional solutions, i.e., single hoisting system with tower layout, single system with headframe layout, and single system utilizing pre-ordered equipment with tower layout. The study evaluates their technical parameters, investment costs, advantages, and disadvantages. Key findings reveal that while the original design involves the highest investment, it benefits from ready-to-use equipment, minimal retrofitting, sufficient hoisting capacity to reliably meet production targets, and the lowest risk.Although single-system options (Options 1 and 2) reduce investment, they entail equipment cancellation (with penalty risks), shaft retrofitting, tight operational capacity, and elevated construction risks.Option 3, despite having the lowest investment, fails to meet demand due to inadequate hoisting capacity.Considering reliability, production stability, and long-term costs, the original design is recommended as the optimal solution.

    参考文献
    相似文献
    引证文献
引用本文

杨国强,邓皓泽,王会来.利用矿山已有工程及设备情况下竖井提升系统方案研究[J].有色设备,2025,39(4):106-111.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2025-03-06
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2025-11-13
  • 出版日期:
文章二维码